Pekerjaan Simpang Susun Semanggi Capai 50 Persen
.
photo Nurito - Beritajakarta.id

Semanggi Interchange Project Reached 50 Percent

The Semanggi Interchange project keeps being accelerated. Until now, it has reached 50 percent and is targeted will be complete in the upcoming July.

Entering week 44, Semanggi Interchange has touched 50 percent

Jakarta Bina Marga Dept Head, Yusmada Faizal disclosed, the Semanggi Interchange project has entered box girder installation on Jl Jenderal Sudirman as long as 45 meters. And its installation would also be done on Jl Gatot Subroto as long as 80 meters.

Tree Pruning Around Semanggi Interchanges Is Illegal

"Entering week 44, Semanggi Interchange has touched 50 percent," he stated, Wednesday (1/11).

Faizal assured it will not disturb traffic around the project site. Considering it is carried out on roadside and do not need to close the road.

"There are 295 box girders ready to be installed. Thus far, 175 out of them were installed," he finished.

Linked News
Popular News indeks
  1. MSMEs Bazaar Held at Binus Anggrek Campus

    access_time30-10-2024 remove_red_eye954 personTP Moan Simanjuntak
  2. 250 High School Students in N. Jakarta Learn to Create Digital Content

    access_time01-11-2024 remove_red_eye660 personBudhi Firmansyah Surapati
  3. Satpol PP Expels Illegal Participants at Sudirman - Thamrin CFD

    access_time27-10-2024 remove_red_eye454 personBudhi Firmansyah Surapati
  4. South Jakarta City Government Accelerates Stop BABS

    access_time31-10-2024 remove_red_eye395 personTiyo Surya Sakti
  5. Traffic Arrangement Applied on Jalan Tambak

    access_time28-10-2024 remove_red_eye370 personAldi Geri Lumban Tobing