Pekerjaan Simpang Susun Semanggi Capai 50 Persen
.
photo Nurito - Beritajakarta.id

Semanggi Interchange Project Reached 50 Percent

The Semanggi Interchange project keeps being accelerated. Until now, it has reached 50 percent and is targeted will be complete in the upcoming July.

Entering week 44, Semanggi Interchange has touched 50 percent

Jakarta Bina Marga Dept Head, Yusmada Faizal disclosed, the Semanggi Interchange project has entered box girder installation on Jl Jenderal Sudirman as long as 45 meters. And its installation would also be done on Jl Gatot Subroto as long as 80 meters.

Tree Pruning Around Semanggi Interchanges Is Illegal

"Entering week 44, Semanggi Interchange has touched 50 percent," he stated, Wednesday (1/11).

Faizal assured it will not disturb traffic around the project site. Considering it is carried out on roadside and do not need to close the road.

"There are 295 box girders ready to be installed. Thus far, 175 out of them were installed," he finished.

Linked News
Popular News indeks
  1. Commission E Urges Residents to Increase Role in Preventing DHF

    access_time19-12-2024 remove_red_eye1223 personDessy Suciati
  2. Transjakarta Adjusting Service as Simpang Pramuka and Rawamangun Bus Stops Closed

    access_time18-12-2024 remove_red_eye1056 personAldi Geri Lumban Tobing
  3. First Jakarta Update Talks Nataru up to Water Tariff Adjustment

    access_time24-12-2024 remove_red_eye1049 personDessy Suciati
  4. Transjakarta, Telkomsel to Improve Service for Customers

    access_time19-12-2024 remove_red_eye912 personAldi Geri Lumban Tobing
  5. Acting Governor Monitors Food Stock at Kramat Jati and Cipinang Markets

    access_time19-12-2024 remove_red_eye737 personFolmer